Section 20 notice of intent to upgrade heating system

rad

This week leaseholders at Bevin Court each received a Section 20 notice of intent for upgrading the heating system here. This follows on from the informal consultation that the council has carried out with the TRA over the last 18 months or so. Leaseholders will be charged for their share of the works, and can email homeownership@islington.gov.uk with their views on this. Sadly, tenants do not have the same statutory rights to be consulted at this stage. If people have strong views about the work and don’t feel they have a voice, let the TRA know and we can channel them to the council using via some of our leaseholders.

Here’s what we posted a while back about the planned works:

While the boiler and heating risers in the boiler house have been replaced in the last ten years, the parts of the system inside the flats are approaching 30 years old and will need replacing soon.

 

PLAN

The plan is to remove all internal pipework, tanks and radiators within each dwelling and replace it on a like for like basis. However there will be some significant improvements;

  • We will have new thermostatic radiator valves, and room thermostats with a time clock, giving a single control for the heating in each flat.
  • The hot water cylinders will be upgraded to give a faster recovery time, meaning that it will be possible to run another hot bath after a wait of only 20 minutes.
  • Unlike the existing Elson tanks, the cold water cylinder will be separated from the hot, meaning that the cold water will no longer be tepid from heat leakage from the hot tank.
  • The new tanks will where possible be placed higher up in the flat, which will improve water pressure, though not to the extent that the pressure would be adequate for showering. This would still require the installation of a pump, something that LBI are not prepared to provide as it would present them with an additional long term maintenance cost.
  • We will get a choice of a heated towel rail or a radiator in our bathrooms.

 

 

There will be no radio controlled thermostats as previous installations in Islington have proved problematic.

 

We will continue to have a 2 pipe system – this means that each flat has both hot water and central heating available all year round. Other flats have a 4 pipe system which allows for the central heating to be turned off in the summer. However it would be prohibitively expensive to convert Bevin Court to this system as the layout of the plant room would have to be substantially altered and there is not sufficient space to do so.

 

WORKS

In terms of the works inside the flats, the plan is that each dwelling will be surveyed individually, with a design for the work agreed in advance with the specific tenant or leaseholder. The works will be loud, as they will require drilling into the concrete of the building, and will be carried out between 8am and 5pm Monday to Friday. There will not be any scaffolding.

 

The work in each dwelling will take place over a week, with the ambition that it can be completed in three days per flat. No home will be left without hot water in the evenings. The works are to be planned for Spring & Summer months, so that heating should not be necessary for most residents.  Should heating be required while the works are underway in our flats, the council will lend us electric heaters. There will be considerable disruption during the work, as the contractors will have to get access to all pipework and radiators throughout the flat.

 

Any pipes that are currently boxed in will be boxed in again at the end of the job, but in general the new pipework will be left exposed. All new pipework will be painted white. The new radiators are likely to be smaller than existing; therefore residents may have to make good the paintwork around the new installation. Any existing pumps that residents have in their flats will be tested and connected to the new system.

 

COSTS AND SCHEDULE

The costs recharged to leaseholders are still to be determined, following the evaluation of the tendering process. The target start date for the work is Spring 2017. The key factor in keeping the project on schedule is to get access when required to each flat. The Islington Project Managers see the experience of the first few residents to have the works carried out as critical; if they are happy then the word will spread and other residents will be more willing to cooperate with the contractors. If this is a success then multiple teams can work across the building and works should be completed between April and October.

 

The work will be put out to tender. The TRA have asked for potential contractors to be selected on the basis of having experience of working on other listed buildings. There will initially be site meetings every two weeks, moving to monthly once the project is running smoothly. There will be permanent site office here on a location to be decided, though this is likely to be in the car park. There is a possibility of a respite area being provided for residents who wish to escape the noise & disruption during works in their flat.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s